7.9 Exhaust valve
7.9.1 Exhaust valve - remove
Periodicity
Description
One Time - after first working hours 18 000
Working hours 36 000
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate AR
Support equipment
Description Part No. CSN QTY
Sling 94049A 2
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
CAUTION
To prevent injury top personnel and damage to equipment, use only the correct lifting
equipment to lift and move the expansion piece.
PRELIMINARY OPERATIONS
• The engine must be stopped and made safe for maintenance, refer to section 4.1 Do
maintenance work - general procedure
X72DF
AA00-2751-00AAA-520A-A
Maintenance Manual Exhaust valve - remove
Winterthur Gas & Diesel Ltd.
- 292 - Issue 002 2020-10