11.3.2 Scavenge air cooler - install
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 2.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Basic AR
Support equipment
Description Part No. CSN QTY
Trolley 94015F 2
Lever chain hoist 94016-x-x 2
Lever chain hoist 94016-y-y 1
Spur-geared chain block 94017-z-z 1
Shackle 94018X 2
Chain 94019A/B 1
Swivel lug 94048-Mxx 6
Left support 94663A 1
Right support 94663B 1
Support 94663L 1
Ring 94666A 1
Supplies
Description QTY
None
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
WARNING
To prevent injury, use only the correct equipment to lift and move the scavenge air
cooler.