10.7.3 Flow limiting valve - install
Periodicity
Description
Working hours 48 000
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 1.0 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate 1
Support equipment
Description Part No. CSN QTY
None
Supplies
Description QTY
Never Seez NSBT A/R
Spare Parts
Description Part No. CSN QTY
Flow limiting valve
(complete or only related
parts)
pc 1
SAFETY PRECAUTIONS
CAUTION
Injury hazard. To prevent injury, use two or more personnel to lift and move the flow
limiting valve.
PRELIMINARY OPERATIONS
• None
X72DF
AA00-5565-00AAA-720A-A
Maintenance Manual Flow limiting valve - install
Winterthur Gas & Diesel Ltd.
- 608 - Issue 002 2020-10