12.2.3 Integrated electric balancer - remove the bearing (outer side)
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements 0.0 man-hours
Duration for performing the procedure 0.5 man-hours
Duration for performing the requirements after job completion 0.0 man-hours
Personnel
Description Specialization QTY
Engine crew Intermediate AR
Support equipment
Description Part No. CSN QTY
Lifting tool 94704 1
M20 x 140 mm screws NA 2
Supplies
Description QTY
Oil AR
Spare Parts
Description Part No. CSN QTY
None
SAFETY PRECAUTIONS
CAUTION
Injury Hazard: Use the correct equipment to lift and move the bearing. This will prevent
injury to personnel and damage to equipment.
CAUTION
Damage Hazard: Do not remove two bearings at the same time. Damage to the equipment
can occur.
PRELIMINARY OPERATIONS
• Do the procedure in section 12.2.1 Integrated electric balancer - prepare before the
bearings removal
X72DF
AA00-7758-00AAA-520B-A
Maintenance Manual Integrated electric balancer - remove the bearing (outer side)
Winterthur Gas & Diesel Ltd.
- 694 - Issue 002 2020-10