First commissioning of SIMATIC IPCs
3
3.1 Overview
After you have completed the first commissioning of yoursupported SIMATIC IPC
configuration (Page 7) with the PCU-Basesoftware, you can configure the SIMATIC IPC like
a SINUMERIK PCU.
You can find an example workflow of the first commissioning and configuration in this tabular
overview.
Note
Do not switch off SIEMENS PC systems with Windows 7 on the hardware!
Loss of data may result on Windows-based systems if the system is not shut down properly
before it is disconnected from the power source. For technical reasons, data is still being written
to the SSD shortly after shutdown.
To avoid loss of data, use a SITOP UPS module.
See Configuring the SITOP UPS module for use with the PCU Base Software (Page 52).
Example workflow
No
.
Step Description
1 Set up and commissioning
of the PC system (according
to the operating instructions)
Information on setting up and installing your SIEMENS PC system can be found in the corresponding
hardware documentation:
2 Install the PCU-Basesoft‐
ware
If required, adapt the installation settings (Page 26) and install the PCU-Basesoftware (Page 27).
3 Connect the PG/PC To be able to access a directory of a PG/PC in the network, for example, connect the PG/PC in the
network (Page 141).
4 Configure network settings
on PG/PC
Once you have networked the PC system, a PG/PC and any other devices with one another, configure
the network settings of your PG/PC (Page 141).
5 Set up further user accounts Before you install software, at least one user account with limited rights must be set up (Page 30).
6 Install software and updates Install necessary automation software and Windows updates (Page 95).
7 Configure the system Configure the installed software (Page 95), Windows 7 and other system characteristics (Page 29) and,
if necessary, the SITOP UPS module (Page 52).
8 Create a disk image (back‐
up)
Create a disk image of the SSD as a backup (Page 121) to be able to return to this version in a mainte‐
nance situation.
PCU Base Software (IM10)
Commissioning Manual, 12/2017, 6FC5397-1DP40-6BA1 25